Friday 17 April 2015

Catch up with Ryan the SS

We had our catch up with the Building Supervisor today (Ryan) to view the tiles to make sure they were the right ones. Good news is they are.



He also advised they were going to start bricks today, however the rain kind of killed that idea. So fingers crossed we get a start with bricks next week. The sand was Delivered.


All the Wet Area Tiling will start next week, and the cornice work will finish next week as well.
After the tiling is done, we should have the benchtops get installed in 2 weeks and also have the painting start. However the Brickwork does now need to be done for the painters to be able to start their part, as the eaves need to be installed and the Alfresco area needs to be finished.