Monday 13 July 2015

PCI Booked!

Final Inspection booked for the 23rd of July. We are almost there. The Vinyl flooring has been finished and the carpets go in this Thursday.

The carpenters are there this week doing the Architraves and door finishes. Then the Painters come back in to fix the Plasterboard and touch up everything.

Our Gutters at the front of the house are being fixed as 1 side was too short, and the other wasn't sealed 100%, and the Bag n Paint needs to be applied again.

So hopefully in 10 days, I will walk into a house that doesn't need much done to handover.