Friday 27 June 2014

Waiting!

Just as the title says, *Waiting*.

No news on the registration at all, so we just wait!!!!
The down side is the longer this takes, the more weeks go by where we have to pay the Builder $1000 a month in additional charges on labour costs and material Costs.

This kicks in from July 22nd, so by the time registration comes in, then settlement, then DA approval then retaining walls and then finally construction list, We could be up for 2k to 4k additional charges.

Not happy with that let me tell you.  What doesn't help is the lack of feedback from the vendor. they wonder why people start to get pissed and shitty. Especially when it starts to cost your customers real $$$$.

I need access to the site to conduct the Surveys, so that I can see how much retaining walls we need, and how much this could possibly cost. Cause I'll be honest, if the cost to do the retaining walls exceeds $15k, This will put me in a very tough position, where basically we might have to walk away from the deal.

What shit's me the most, is the fact we weren't advised of the 2 easements in the rear of yard and it's positioning, which forces us to have to put in retaining walls.

The lesson in this for anyone heading into off the plan purchase, *trust no one*, and prepare for the finger pointing fairies to come out in force.